Exercise 5- PERT/CPM: Grasso Construction Company.
In 2018, Grasso Construction Company had received a contract to construct a water purification system for the city of Wilmington. By the fall of 2019, work was nearly complete on the main system; however, it was apparent that work on a special remote control building would have to be finished earlier than originally planned if the main system was to be completed on time.
Mr. Jason Barnes, field construction supervisor for Grasso Construction Company had arranged a meeting with Ms. Addison Lee, project engineer, to restudy the arrow diagram of their critical path schedule for the construction of the remote-control building in an effort to determine the shortest possible time in which the job could be done without spending more money than necessary.
Grasso Construction used the Critical Path Method as a tool to assist in project planning and control. A list of the activities for the remote-control site is in Exhibit 1. The Cost Table, Exhibit 2, lists the activities and their duration along with the cost needed to complete them in this “normal time”. The Cost Table also lists the minimum amount of time that each activity will require, called the “crash” time. In addition, a final listing in the Cost Table shows how much it will cost to shorten each activity by one week. The sequence of consecutive activities requiring the longest time to complete before the end of the project is known as the “critical path” for that project. The path is considered “critical” because any delay in the particular sequence will delay the completion of the entire project.
Exercise 5- PERT/CPM: Grasso Construction Company.
Exhibit 1
Job Label | Job Description | Immediately Preceding Job | Normal Time te | tp |
A | Procure materials | Start | 3 | 4 |
B | Prepare site | Start | 6 | 8 |
C | Prepare request for Wilmington Engineering department approval | Start | 2 | 3 |
D | Prefabricate building and deliver to site | A | 5 | 7 |
E | Obtain Wilmington Engineering department approval | C | 2 | 3 |
F | Install connecting lines to main system | A | 7 | 8 |
G | Erect building and equipment on site | B, D, E | 4 | 6 |
Exhibit 2
Normal | Crash | |||
Activity | te (Weeks) | Dollars | to (Weeks) * | Dollars** |
A | 3 | $ 5,000 | 2 | $ 5,000 |
B | 6 | $ 14,000 | 4 | $ 6,000 |
C | 2 | $ 2,500 | 1 | $ 2,500 |
D | 5 | $ 10,000 | 3 | $ 4,000 |
E | 2 | $ 8,000 | 2 | – |
F | 7 | $ 11,500 | 5 | $ 3,000 |
G | 4 | $ 10,000 | 2 | $ 7,000 |
Total Project Cost (No Crashing) |
$ 61,000 |
*Crash weeks shown represent the minimum possible time for the given activity, to.
**This is the cost of gaining one week over the normal time by use of “crash” methods.
Exercise 5- PERT/CPM: Grasso Construction Company.
Answer the following questions regarding Grasso Construction Company. Be sure to answer every single question in each individual part.:
**create PERT diagram here***
Paths | Weeks |
Exercise 5- PERT/CPM: Grasso Construction Company.
(highlight new critical path(s) after crashing)
Paths | Weeks |
(*note when crashing, I find it easiest to highlight or color my text for each critical path differently to see if there are any overlaps)
Activity | te (Weeks) | to (Weeks) * | Crashing Cost | Weeks to Crash
(Te-To) |
Goal to get to 10 weeks by crashing
****put updated PERT diagram****
(use this grid to put original paths for comparison)
Paths | Weeks |
Paths | Weeks |
(*note when crashing, I find it easiest to highlight or color my text for each critical path differently to see if there are any overlaps.)
Activity | te (Weeks) | to (Weeks) * | Crashing Cost | Weeks to Crash |
Goal to get to 10 weeks by crashing
Paths | Weeks |
Exercise 5- PERT/CPM: Grasso Construction Company.
(*note when crashing, I find it easiest to highlight or color my text for each critical path differently to see if there are any overlaps. In this case, if you have multiple critical paths, you need to make sure you crash either one activity on both paths or a combination of activities on the two critical paths that is less than or equal to the 10K penalty. This would count as one step.)
Activity | te (Weeks) | to (Weeks) * | Crashing Cost | Weeks to Crash |
Goal to get to 6 weeks by crashing
Explain result: _____________________________________________________
Goal to get to 6 weeks by crashing-
Explain result: ____________________________________________
(Refer to the “Example Using LP” video)