Assignment 1
Answer the following questions. Every question requires you to answer in a certain way which is indicated there.
You answer must be based on Model Law, Arbitration Act, 1974 of Australia as amended, NY Convention, UNCITRAL Rules, ACICA Rules, and relevant IBA Guidelines.
If different laws say differently on a point then you may answer on any one but indicate which law or rules you are using to answer that question.
Give Short Answers (1-3 sentences maximum with reference to the relevant law) to the following Questions
- If the parties include an arbitration clause in a contract, are they allowed to go to court? (1 mark)
- What main differences can you find between article 8 of the Model Law and Article II.3 of the New York Convention? (1 mark)
- What are the consequences if one of the parties to a contract containing an arbitration clause files a lawsuit on a matter included in the arbitration clause?(1 mark)
- At what moment during the proceeding must the defense of lack of jurisdiction of the tribunal be raised contending invalidity of the main contract? Can such defense be raised by the party who participated in the appointment of the arbitrators? (1 mark)
- What legal consequences normally arise from the seat of the arbitration? Is it advisable to agree on a country or a city? (1 mark)
- Which courts may conceivably have jurisdiction to make a default appointment of arbitrator? (1 mark)
- May an arbitrator be of the same nationality as one of the parties? (1 mark)
- What if an arbitrator is from the same law school and law school class as a lawyer representing one of the parties? Should those arbitrators be screened out on account of their group affiliation? (1 mark)
- Is it possible to raise the issue of the challenge to arbitrator in New York Convention countries at the time the award is sought to be enforced? (1 mark)
- May an arbitrator who is a partner in a law firm be allowed to disclose information about the case in arbitration to one of his partners? (1 mark)
- What do you understand by the term “party autonomy”? (1 mark)
- Are there any matters that may restrict the parties’ability to agree on them the procedure for an arbitration? What are those matters? (1 mark)
- If the UNCITRAL Rules have been agreed upon by the parties to govern the conduct of the arbitration, but the parties have not agreed on the number of arbitrators to be appointed to hear the case, how many arbitrators would be appointed? (1 mark)
- How would an arbitration ordinarily be commenced? (1 mark)
- What recourse, if any, would a claimant have if a respondent fails to serve a statement of defence in accordance with a direction or order from the arbitral tribunal? (1 mark)
- What is a “documents only” arbitration? (1 mark)
- If one party fails to attend the hearing, what can the other party or the tribunals do? (1 mark)
- Does emergency arbitration tribunal need to consider its jurisdiction? (1 mark)
- Is there a difference between the selection of the law applicable to a contract and the law applicable to an arbitration agreement? (1 mark)
- What is the difference between a“decision”of the arbitral tribunal and an award? (1 mark)
- What is meant by a “final award”? (1 mark)
- How might a settlement reached in a conciliation proceeding become an award on agreed terms in arbitration? (1 mark)
- Can a settlement award be enforced under the New York Convention? (1 mark)
- If the arbitral tribunal is composed of more than one arbitrator, how many have to vote for the award? (1 mark)
- What are the requirements for the form and content of an award? (1 mark)
- Must the award be written under all circumstances? (1 mark)
- If there is more than one arbitrator, how many of them must sign the award? (1 mark)
- What are the functions of requiring the date and the place of arbitration on the award? (1 mark)
- Can an award be issued without reasons? (1 mark)
- If the arbitral tribunal rules that it has jurisdiction, when can the respondent appeal the decision to the national court? (1 mark)
- The courts of which jurisdictions are well situated to collaborate or interfere (positively) with an arbitration? (1 mark)
- What are the differences between refusing recognition and enforcement of an award and setting it aside? (1 mark)
- Which is the proper court which has jurisdiction to set aside an award? (1 mark)
- Which law regulates the grounds upon which an award may be set aside? (1 mark)
- Is it absolutely impossible to enforce an award set aside at the seat of arbitration? (1 mark)
- What formal requirements must a party satisfy when applying for the recognition and enforcement of an award? (1 mark)
- Is a party allowed to rely on any ground other than those expressly mentioned in NY Convention? (1 mark)
- What is the purpose of the ICSID Convention? (1 mark)
- Does participation of a State in the Convention entail consent to jurisdiction in ICSID proceedings? (1 mark)
- In what way may the parties give consent to jurisdiction in investment arbitration? (1 mark)
Assignment -2
Smart Publication Company against The New Zealand Machine and Tools Company
Facts
- Smart Publication Company (SPC) is a company which was set up in Melbourne Australia in 2015. SPC mainly focuses on publishing academic books (“the books”) which are used in the Australian tertiary education institutions. In order to reduce the cost of publication of the books, SPC decided to establish a printing press in Fiji. After printing the books in Fiji, SPC arranges for the delivery of the books into Australia and then sells them through shops in Australia including bookshops in Universities.
- In March 2015, SPC contacted the New Zealand Machinery and Tools Company (“NMTC”) to purchase the various machinery (“the various machinery”) which was needed for its book printing business such as printing machines, sewing machines, binding machines and individual binding and wrapping machines. In particular, SPC was also looking for heavy duty machinery which can operate for long hours without any breakdown. After intense negotiations lasting two months the parties finally entered into a contract (“the first contract”). It was a term of the contract that SPC will pay in half yearly installments to be fully paid by 2019 to purchase the various machinery to build a printing press (“the original printing press”) in Fiji (“the Fiji facility”). See further details as to the terms of first contract in Exhibit/s [1 ] and [2 ].
- During the negotiations NMTC also informed SPC that a fully automated and one-stop machine (“the new machine”) would be launched in the printing market in the second half of 2016 which would, in all likelihood, revolutionize the book printing process. In this regard, instead of having to buy the various machinery a printer could just buy the new machine. The new machine was being produced by a German company, Book Printing Wizard Machine (BPWM), as a joint venture with NMTC. It was expected that the total cost of the new machine might be more than double the total cost of the various machinery. SPC, being a new entrant in the market and also to expedite the launch of their books, decided to buy various machines. Both parties agreed to revisit the purchase of the new machine on a later date.
- Over a short period following conclusion of the contract SPC acquired a significant portion of the booming book market in Australia and it also acquired a number of clients from overseas. Currently, some of SPC’s clients also agreed to get their books printed at the Fiji facility to save their costs. Of course, SPC charges these clients money to recover its costs and to make a profit.
- In early 2017, SPC contacted NMTC to discuss the possibility of SPC buying the fully automated one-stop machine as it (SPC) was thinking of setting up another printing unit in Fiji. During these negotiations, SPC stated it was mainly concerned with the speed of the new machine and it was expecting that the new machine produce at least 30 books per hour. NMTC advised SPC that it was hopeful that the new machine would perform up to SPC’s expectations in this respect but that NMTC could not be definitive. Finally, SPC agreed to buy one new machine from NMTC (“the second contract”), Pursuant to the second contract, the new machine was duly delivered by NMTC to the Fiji facility and installed and also tested there by NMTC. See further details as to the terms of second contract in Exhibit/s [3 ] and [4 ].
- In the very first month its operation, SPC realized that the new machine was not performing up to its expectations. The new machine was barely producing 15-20 books per hour. After SPC made a complaint to NMPC about this problem (“the first problem”), NMPC arranged for BPWM technicians of BPWM to look at the new machine and to repair. After completing these repairs, the new machine started producing around 20-25 books per hour. A few months later, the new machine started slowing down the number of books it could print again. The original printing press also was not operating at full capacity because of a problem with over-heating. As a result, after every eight hours the original printing press had to be shut down for almost four hours (“the second problem”). The CEO of SPC became fed up with the first and second problems and decided to terminate the contact with NMTC and, in addition, to withhold payment on the outstanding amount owing in relation to the new machine as well as the outstanding installments owing in relation to the purchase of the various machinery used to build the original printing press.
- In order to recover payments due under the first and the second contract NMTC initiated arbitration proceedings in Sydney which was to be administered by ACICA using the ACICA rules. The ACICA appointed a sole arbitrator to hear both claims for payments under the first and second contracts. SPC has objected to the jurisdiction of the arbitral tribunal.
- Australia, New Zealand, and Fiji are all signatories to the New York Convention on Recognition and Enforcement of Foreign Arbitral Award, and have adopted Model Law on International Commercial Arbitration (2006 Amendment with Option I of Article 7)
- The President of the arbitral tribunal has asked both parties to provide him with written submissions on the following issues at the arbitration hearing:
- Whether there is a valid arbitration Agreement?
- Which arbitration rules are applicable to this arbitration?
- Where is the seat of arbitration and where should be the place of hearning?
- Whether the same arbitration tribunal can hear the two payment claims?
- Would there be any risk of enforcement of the arbitral award rendered by this tribunal?
(Note: Students can answer these questions on behalf of either the Claimant (NMTC) or the Respondent (SPC). But students must answer/argue all three questions on behalf of one side only. Students cannot choose different sides for different issues. Student may also decide the case like an arbitrator but in this case as an arbitrator you need to consider/raise arguments from both sides and then give decision like an arbitrator.
Exhibit -1
(By e-mail)
1 May 2015
To
Richard Booker
CEO, SPC
Re: Purchase of printing machines from NMTC to SPC.
Dear Mr. Booker
After two months of discussion, I am glad that we have finally reached the stage where I am able to send you our contract for the purchase of printing machines. As we have agreed, all these machines will cost you AUD$5 million in total, inclusive of delivery, installation, testing and repairing. SPC will have to pay NMPC AUD$1 million immediately and the remainder of the monies owing will be paid in half yearly installments from now until the end of 2019.
As you have suggested that we use arbitration to resolve any disputes arising out of this contract we are ready to accept that. I should tell you that generally, we agree to arbitrate in Auckland and to use NZ Arbitration Rules. We are also willing to arbitrate in Sydney in accordance with the ACICA Rules. I read that now Australia also has a new Arbitration Centre in Perth so would it be too inconvenient for you to use the Perth Arbitration rules instead?
I wish you all the best for your business.
Regards
Daan Mechanics
CEO, NMTC
Exhibit-2
(by e-mail, 2 May 2015)
Dear Danny
I hope you don’t mind if I call you Danny instead of Daan as your name is difficult for me to write and pronounce.
I am very happy that we have finally entered into a business relationship and I do hope it is a long term one. As I told you during our discussion I will contact you again in relation to conducting future business. Don’t worry about payments as I will transfer these into NMTC’s bank account as per our agreed schedule.
I am happy that you agreed to arbitration in Sydney. It is correct that Perth now has an Arbitration Centre. I can understand that you are familiar with Perth Rules but ACICA rules are also satisfactory. You will not be disappointed with the ACICA rules. You should try new things in life!
Best
Richard
Exhibit-3
(By e-mail, 14 February 2017)
Dear Danny,
You may recall that we discussed SPC buying NMTC’s and BPWM’s one-stop fully automatic printing machine last time but I could not buy it at that time. Now my business is roaring and I want to expand it. In this regard I am writing to you to see if the machine is now available in the market and how much it will cost me. I hope you will give me a discount, as I am your old friend.
I want this new machine to produce at least 30 books per hour. Your old machine is not working as per my expectation. Although your mechanics have repaired it twice, it has started heating up again which is slowing down my production.
Best
Richard
Exhibit – 4
(By e-mail, 15 February 2017)
Dear Richard,
It is so nice to hear from you after a long time.
We have launched our one-stop automatic machine and I am happy to tell you that it is in high demand.
While I cannot be absolutely definitive about this, I am optimistic that this machine will perform up to your expectations.
The machine will certainly cost you more but being my old business partner I will give you a discount. It will cost you AUD$7 million although our usual market price is AUD$8 million. Our price again includes delivery, installation, testing and repairing. You just have to pay NMTC AUD$2 million immediately and the remaining monies in half yearly installments to be fully paid by the end of 2019.
This time I hope you will agree to use the Perth Arbitration rules in Sydney for arbitrating any dispute which may arise out of this contract.
Regards
Danny
Exhibit No-5
(e-mail, 20 February 2017)
Dear Danny,
As we spoke on the phone yesterday, I confirm that SPC will buy the new machine and price is agreeable to me.
I can see that you are still interested in using the Perth Arbitration Rules in Sydney should the need for arbitration arise. But I recommend instead that we agree to apply the same rules i.e. ACICA Rules. I have heard the new ACICA rules are equal if not better than the Perth Arbitration rules.
Best
Richard
Exhibit No-6
(E-mail, 14 January 2018)
Dear Danny,
I am writing this letter in great pain and frustration. Your new machine is very slow and it is producing only 15-20 books. After the first repairs were carried out by your mechanic it only produced between 20-25 books for a period of one month after these repairs. Now it is slowing down again. Your old machine has started heating up again therefore I have to shut down the old machine every now and then. I paid so much money for a quality machine but I am sorry to say that both machines are useless. So I am not going to pay any money now, until you fix these machines. But your mechanic informed me that both the old and the new machine cannot be repaired; therefore, I am going to terminate both the contracts and no further monies will be paid to you.
Best
Richard
Instructions to Students
Students can answer these questions on behalf of either the Claimant (NMTC) or the Respondent (SPC). But students must answer/argue all questions on behalf of one side only. Students cannot choose different sides for different issues. Students may also decide the case like an arbitrator but in this case as an arbitrator students need to consider/raise arguments from both sides and then give decision like an arbitrator.
- Whether there is a valid arbitration Agreement?
- Which arbitration rules are applicable to this arbitration?
- Where is the seat of arbitration and where should be the place of hearning?
- Whether the same arbitration tribunal can hear the two payment claims?
- Would there be any risk of enforcement of the arbitral award rendered by this tribunal?
Word Limit : 2000 words (maximum) not including cover page, bibliography, footnotes, endnotes.
Further Instruction
You may note that for this exercise there is no one answer. Every answer will be considered as a persuasive answer as long it is based on given facts and relevant law. You are required to demonstrate your understanding of law and its application on the given facts to reach your conclusion. These facts are hypothetical and you should take it as established facts.

