Helping the world grow since 2012
Call/WhatsApp/Text +1(838)201-9170

  • HOME
  • STUDY RESOURCES
  • ABOUT
    • About Apax Researchers
    • Why Do Students Use Us
    • Why Choose Us
    • Contact Us
  • BECOME A WRITER
  • BLOG
    Login
    Sign Up
    Helping the world grow since 2012
    Call/WhatsApp/Text +1(838)201-9170

    • HOME
    • STUDY RESOURCES
    • ABOUT
      • About Apax Researchers
      • Why Do Students Use Us
      • Why Choose Us
      • Contact Us
    • BECOME A WRITER
    • BLOG
    Login
    Sign Up
    Helping the world grow since 2012
    Call/WhatsApp/Text +1(838)201-9170

    • Write My Essay: Perfect Cheap Essay Writing Service for You
    • ABOUT
      • About Apax Researchers
      • Why Do Students Use Us
      • Why Choose Us
      • Contact Us
    • BECOME A WRITER
    • BLOG
    • QUESTIONS AND ANSWERS
    • LOGIN
    • SIGN UP

    Describe TWO objectives of Boeing’s Dreamliner development strategy (5pts each answer). Objective 1: Objective 2:

    1.Describe TWO objectives of Boeing’s Dreamliner development strategy (5pts each answer).

    Objective 1:

    Objective 2:

    2.Select TWO of the following types of failure and describe how they were exhibited by Boeing in its Dreamliner development strategy (10pts each answer).

    1. a)  Market failure
    2. b)  Operational failure
    3. c)  Financial failure
    4. d)  Strategy failure

    3.Boeing’s default framework when deciding its Dreamliner development strategy was that changing its traditional design and manufacturing process for a new and innovative aircraft would save time and costs. Name TWO assumptions underlying Boeing’s default framework that proved to be false (5pts each answer).

    Assumption 1:

    Assumption 2:

    4.What were the proximate, intermediate, contributory and root causes of Boeing’s Dreamliner production delays and cost overruns? Briefly explain your answers (5pts each answer).

    Proximate cause(s)

    Intermediate cause(s):

    Root cause(s):

    Contributory factor(s):

    5.Select ONE of the following failure modes that could have been analyzed in a FMEA before Boeing’s decision to outsource 70% of the Dreamliner’s development and manufacturing (10pts).

    Briefly describe the consequences and estimate the severity and probability of your selected failure mode, based on what Boeing knew in  2003.

    1. a) Innovative component design and materials fail to deliver lower fuel costs and more comfortable on-board ventilation.
    2. b) Innovative component design and materials create manufacturing problems.
    3. c) Boeing engineers fail to adequately oversee outsourced production.
    4. d) Suppliers lack experience manufacturing with composite materials.
    5. e) First- and second-tier suppliers lack experience sub-contracting production to second- and third-tier suppliers.
    6. f) Exostar development tracking system does not accurately report suppliers’ progress.

    Component:

    Potential consequences:

    Probability (%) of occurrence:

    Severity of impact (1 = low, 5 = high):

    6.Select a SECOND one of the following failure modes that could have been analyzed in a FMEA before Boeing’s decision to outsource 70% of the Dreamliner’s development and manufacturing (10pts).

    Briefly describe the consequences and estimate the severity and probability of your selected failure mode, based on what Boeing knew in  2003.

    1. a) Innovative component design and materials fail to deliver lower fuel costs and more comfortable on-board ventilation.
    2. b) Innovative component design and materials create manufacturing problems.
    3. c) Boeing engineers fail to adequately oversee outsourced production.
    4. d) Suppliers lack experience manufacturing with composite materials.
    5. e) First- and second-tier suppliers lack experience sub-contracting production to second- and third-tier suppliers.
    6. f) Exostar development tracking system does not accurately report suppliers’ progress.

    Component:

    Potential consequences:

    Probability (%) of occurrence:

    Severity of impact (1 = low, 5 = high):

    7.Select a THIRD one of the following failure modes that could have been analyzed in a FMEA before Boeing’s decision to outsource 70% of the Dreamliner’s development and manufacturing (10pts).

    Briefly describe the consequences and estimate the severity and probability of your selected failure mode, based on what Boeing knew in  2003.

    1. a) Innovative component design and materials fail to deliver lower fuel costs and more comfortable on-board ventilation.
    2. b) Innovative component design and materials create manufacturing problems.
    3. c) Boeing engineers fail to adequately oversee outsourced production.
    4. d) Suppliers lack experience manufacturing with composite materials.
    5. e) First- and second-tier suppliers lack experience sub-contracting production to second- and third-tier suppliers.
    6. f) Exostar development tracking system does not accurately report suppliers’ progress.

    Component:

    Potential consequences:

    Probability (%) of occurrence:

    Severity of impact (1 = low, 5 = high):

    8.Select a FOURTH one of the following failure modes that could have been analyzed in a FMEA before Boeing’s decision to outsource 70% of the Dreamliner’s development and manufacturing (10pts).

    Briefly describe the consequences and estimate the severity and probability of your selected failure mode, based on what Boeing knew in  2003.

    1. a) Innovative component design and materials fail to deliver lower fuel costs and more comfortable on-board ventilation.
    2. b) Innovative component design and materials create manufacturing problems.
    3. c) Boeing engineers fail to adequately oversee outsourced production.
    4. d) Suppliers lack experience manufacturing with composite materials.
    5. e) First- and second-tier suppliers lack experience sub-contracting production to second- and third-tier suppliers.
    6. f) Exostar development tracking system does not accurately report suppliers’ progress.

    Component:

    Potential consequences:

    Probability (%) of occurrence:

    Severity of impact (1 = low, 5 = high):

     

     

    CASE STUDY 1 Boeing Dreamliner Your name Max Points 100
    Question 1 (5pts each answer, 10pts total)
    Describe TWO objectives of Boeing’s Dreamliner development strategy.

     

     

    Question 2 (10pts each answer, 20pts total)
    Select TWO of the following types of failure and describe how they were exhibited by Boeing in its Dreamliner development strategy:

    –          Market failure

    –          Operational failure

    –          Financial failure

    –          Strategy failure

     

     

    Question 3 (5pts each answer, 10pts total)
    Boeing’s default framework when deciding its Dreamliner development strategy was that changing its traditional design and manufacturing process for a new and innovative aircraft would save time and costs. Name TWO assumptions underlying Boeing’s default framework that proved to be false.

     

     

    Question 4 (10 pts for each part, 40pts total)
    Select FOUR of the following failure modes that could have been analyzed in a FMEA before Boeing’s decision to outsource 70% of the Dreamliner’s development and manufacturing. Briefly describe the consequences and estimate the severity and probability of each of your selected failure modes, based on what Boeing knew in  2003.

     

    Failure Mode Potential Consequences Severity Score* Probability %
    Innovative component design and materials fail to deliver lower fuel costs and more comfortable on-board ventilation      
    Innovative component design and materials create manufacturing problems      
    Boeing engineers fail to adequately oversee outsourced production      
    Suppliers lack experience manufacturing with composite materials      
    First- and second-tier suppliers lack experience sub-contracting production to second- and third-tier suppliers      
    Exostar development tracking system does not accurately report suppliers’ progress      

     

    *Severity scale: 1 = low, 5 = high

    Question 5 (5pts for each answer, 20pts total)
    What were the proximate, intermediate, contributory and root causes of Boeing’s Dreamliner production delays and cost overruns?

    Briefly explain your answers.

     

    Proximate cause(s):

     

    Intermediate cause(s):

     

    Root cause(s):

     

    Contributory factor(s):

     

     

     

     

    There are four case studies throughout the course. In these case studies, you will unpack and explain the application of course principles to real contexts. These cases serve as test runs of the Business Impact Analysis assignment, in that they’re intended to help you think through the myriad issues at play in identifying risk within a company or industry.  These case studies are synchronized with the provided reading materials.

    For case study #1, review the Boeing Dreamliner case study, then answer questions 1-8. Copy and paste the question which you’re answering into the answer box. Be precise and limit each answer to 75 words or less.

    if you wish to draft your answers before submitting them, you may use this word document

     

     

     

    CITATION

    Share
    GET A FREE QUOTE






      

    Why Choose US

    Affordability & Discounts
    Dedicated Support Team
    Timely Delivery
    Money Back Guarantee
    Zero Plagiarism
    Great discounts
    Top Writers
    Adherence to Instructions

    Recent Posts

    • Common App Essay Prompts
    • Transition Words: Examples and When and How To Use Them
    • Research Paper Topics
    • Best Argumentative Essay Topics
    • How to Write a Cover Letter

    If you need writing solution... We are available for you

    Place your order now and one of our writers will begin working on your assignment right away.

    Order NOW!

    From Our Blog
    • 0
      Common App Essay Prompts
      August 9, 2022
    • 0
      Research Paper Topics
      August 8, 2022
    Services
    • Research
    • Writing
    • Summary & Editing
    • Programming & Tech
    • Graphics & Design
    • Transcription
    • Digital Marketing
    • Lifestyle

    Social Media

    Subscribe here to get interesting stuff and updates!

    whatsapp Image
    Let's chat

    Copyright © 2020 Apax Researchers - All Rights Reserved.

    Legality

    Terms of Use