Basic Subject Matter of Report
Construction Contracts and Dispute Resolution.
Course Context
Masters Course in Quantity Surveying. Equally relevant to International Construction Project Management masters.
Report Requirements
Scenario
The Employer has contracted the Contractor to build the road network for their new housing development. The works contract also includes for the Contractor to design and install the street lighting complete with the necessary fittings and fixtures.
The two parties successfully negotiated and signed FIDIC’s Conditions of Contract for Construction for Building and Engineering Works designed by the Employer, Second Edition 2017, with no need to incorporate any modification in the Special Provisions.
Works started on site on Monday, 6th January 2020. And, the two contracting parties have cooperated amicably until when the Employer refused to pay in full July’s Interim Payment Certificate (IPC). They assert that the level of workmanship, for that part of the works around the junction where their sales offices are located, is substandard due to some key site personal needing to self-isolate as a result of the ongoing coronavirus (COVID-19) pandemic, and that part was done by temporary staff who have not worked with the Contractor previously. Indeed, there were three weeks in July when there were no site activities. the Contractor is not happy about not receiving their full payment, and have been demanding it ever since.
The site had to close again in the first three weeks of September, as several more key staff were self-isolating. And, for this, the Contractor has this time put in a request for extension of time (EOT) citing this as ‘an exceptional circumstance’, and also asked for more money, as a result. Both requests were summarily rejected by the Employer on 5th October.
The Contractor is not at all happy and the two parties’ relationship has now deteriorated, as shown in the timeline of events:
30th November 2020: still at a stalemate, with none of the parties doing anything to amicably resolve their differences, the Employer has now approached your firm of consultants for advice. They wish to refer the dispute to a DAAB, whose members are yet to be appointed, as they found no need for them at the start with the very good working relationship the two parties enjoyed.
Key Concepts/Definitions in Scenario
IPC (Interim Payment Certificate): a concept created within the FIDIC standard form mentioned in the scenario. Essentially a request for payment issued by the Contractor in this case.
Special Provisions: a concept created within the FIDIC standard form mentioned in the scenario. These would supplement the standard form terms and conditions but, as the scenario sets out, are unused.
EOT (Extension of Time): a concept created within the FIDIC standard form mentioned in the scenario. A lever under the contract for the Contractor to move where its initial programme will be subject to delay; EOT isn’t an unconditional contractual right of course; rather, it can be levered only where certain circumstances and/or events have occurred.
Delay Damages: self-explanatory concept (commonly understood as liquidated damages) under the aforesaid standard form contract, pre-agreed amount(s) as a Employer’s remedy for delay.
Performance Security: again, under the contract, a lever or remedy for the Employer against the Contractor connected to its performance obligations/failure to discharge those.
DAAB (Dispute Avoidance and Adjudication): concept (board of people) created within aforesaid standard form. Disputes are referred to the DAAB and it issues binding decisions; it can also provide informal advice and assistance during the contract to the parties before a dispute crystallises (i.e. to avoid that). The DAAB’s actions can of course be undermined by a court, subject to the rest of the agreement in dispute.
FIDIC Contract Data
Sub-Clause | Data to be given | Data |
1.1.85…………… | Time for Completion: | 365 days |
1.4………….…… | contract shall be governed by the law of: | Scotland |
4.2…………..…… | Performance Security (as percentages of the Accepted
Contract Amount in Currencies): percent: ……………………………………………………………………….. currency: ……………………………………………………………………… |
10 %
Pound Sterling |
8.8…………. | Delay Damages payable for each day of delay………………………….. | £5,000.00 |
8.8…………. | maximum amount of Delay Damages …………………………………………… | £500,000.00 |
12.2…………. | method of measurement ………………………………………………………..……… | Bill of Quantities |
14.2…………. | total amount of Advance Payment (as a percentage of
Accepted Contract Amount) ……………………………………………………… |
20 % |
14.2…………. | currency or currencies of Advance Payment …………………………… | Pound Sterling |
14.3(iii) ……… | percentage of retention ……………………….……………………………………. | Not Applicable % |
14.7(b)(i)……… | period for the Employer to make interim payments to the
Contractor under Sub-Clause 14.6 …………….……………………………… |
28 days |
14.8………………. | financing charges for delayed payment (percentage
points above the average bank short–term lending rate as referred to under sub-paragraph (a))…………………………………. |
2 % |
14.15……….. | currencies for payment of Contract Price: | Pound Sterling |
14.15(a)(i) ….. | proportions or amounts of Local and Foreign Currencies
are: Local …………………………………………………………. Foreign ………………………………………………………. |
£2,500,000.00
Not Applicable % |
21.2…………. | Appointing entity (official) for DAAB members ……………. | Association for Consultancy and Engineering (ACE) |
Referencing
Harvard.
Will expect case law in the main, references to FIDIC clauses, some legislation (e.g HGCRA Act ’96 as amend’d) and perhaps academic commentary (less of the latter).
Word Count Constraints
3500 – 4000 (max).
Apportionment of Marks
Element
|
Max. Mark |
Introduction
|
10 |
Literature review / relevant background research | 50 |
Conclusions /
Recommendations |
20 |
Referencing
|
10 |
Structure / Grammar
|
10 |
High-Level Thoughts on Report Approach
A few discrete issues seem to require dealing with:
Potential Authorities
Case law:
Literature/Reviews:
Access to FIDIC Contract
Available for LexisPSL members; some extracts available online; swaths of the relevant provisions from the contract are available online/Google will pull them up.
Footnote
I’m looking for a report to benchmark my own against as obtaining a pass is critical for me on these modules; I have a good handle on the ask and will have my own report drafted in around ten days so can come-and-go with any questions etc.